Arunachal targets 19 GW hydropower expansion with Rs 1.9 lakh crore investment: Dy CM

Itanagar, Feb 5 : Arunachal Pradesh has set a target to add 19 GW of hydropower capacity with an estimated investment of Rs 1.9 lakh crore as part of a strategic shift towards large and mega projects, Deputy Chief Minister Chowna Mein informed the Assembly on Thursday.

Replying to a question by BJP member Tapi Darang during Question Hour, Mein, who also holds the power and hydropower portfolios, said the state has declared 2025-2035 as the “Decade of Hydropower” to accelerate development in the sector.

He said the northeastern state accounts for nearly 40 per cent of the country’s hydropower potential, with 58,000 MW capacity, positioning the state as a key contributor to India’s clean energy transition and its net-zero emissions target by 2070.

“With central support, the state is reviving 13 stalled hydropower projects with a combined capacity of 12.2 GW and has signed MoUs with four central public sector undertakings (CPSUs) in 2023,” Mein said.

Of these, three projects — Heo (240 MW), Tato-II (700 MW) and Tati-I (186 MW) — have already received approval from the Cabinet Committee on Economic Affairs (CCEA), with work underway at project sites, he added.

The projects are being developed through joint ventures between the state government and CPSUs, with the state holding a 26 per cent equity stake, the deputy chief minister said.

“The Centre is supporting the projects by financing 24 per cent equity through Central Financial Assistance (CFA), capped at Rs 750 crore per project. Under this mechanism, CFA support of Rs 6,565 crore will be extended through equity participation,” Mein said.

He further added that the state will receive 12 per cent free power from hydropower projects and is expected to earn an estimated revenue of Rs 4,520 crore between 2025 and 2035, rising to about Rs 4,100 crore annually thereafter.

Additionally, the projects are likely to generate around Rs 821 crore per year for local area development, while dividends from the state’s equity share are estimated at Rs 1,452.4 crore, the deputy chief minister informed.

The hydropower expansion is also expected to create over 30,000 skilled direct jobs during construction and operation, along with about 16,000 indirect employment opportunities, he added.

Mein informed the House that the hydropower development department has been restructured and made operational, and a policy for restoration of terminated large hydropower projects under special circumstances is in place.

“The government has also proposed a renovate-own-operate-transfer (ROOT) policy for small hydropower projects to attract private investment, optimise asset utilisation and ensure energy security,” he said.

The state is revamping its Small Hydropower Policy 2017, to align with technological advancements in the sector, Mein said.

On major ongoing projects, the deputy chief minister informed that two units with a combined capacity of 500 MW of the 2,000 MW Subansiri Lower Hydroelectric Project have been commissioned, with the remaining three units scheduled for commissioning by March this year.

Full commissioning of all eight units of the project is expected by December this year, Mein said.

The 2,880 MW Dibang multipurpose project is under construction and is targeted for completion by February 2032, he added. (PTI)

Hot this week

Pay hike of Assam ministers, MLAs likely as 3-member panel submits report

Full report likely by Oct 30 Guwahati Sept 25: There...

Meghalaya Biological Park Inaugurated After 25 Years: A New Chapter in Conservation and Education

Shillong, Nov 28: Though it took nearly 25 years...

ANSAM rejects Kuki’s separate administration demand, says bifurcation not acceptable

Guwahati, Sept 8: Rejecting the separate administration demand of...

Meghalaya man missing in Bangkok

Shillong, Jan 10: A 57-year-old Meghalaya resident, Mr. Treactchell...

Meghalaya’s historic fiber paves the way for eco-friendly products and sustainable livelihoods

By Roopak Goswami Shillong, Oct 25: From making earbuds to...

16 labourers killed in Thangsku coal mine blast in East Jaintia Hills

Shillong, Feb 5: In a devastating tragedy, several labourers...

How Budgets and Trade Deals Are Shaping Viksit Bharat

By Dipak Kurmi Imagine the construction of a grand structure,...

The Epstein Files and the Shadows of Power

By Satyabrat Borah The phrase Epstein files has become one...

Congress to go solo in West Bengal polls, contest all 294 seats

New Delhi, Feb 5 : The Congress announced on...

Kuki groups warn community MLAs not to participate in Manipur govt formation

Imphal, Feb 5: Several Kuki groups in Manipur have...
spot_img

Related Articles

Popular Categories