Shillong, Nov 27: The Khasi Students’ Union (KSU) has alleged violation of a government assurance by Shree Cement by continuing its activities at Daistong in East Jaintia Hills.
The KSU said the government had assured that no work by Shree Cement would be allowed until the Fact-Finding Committee (FFC) submits its report.
The entire process, from the public hearing to the functioning of the FFC, has been reduced to an eyewash to push the project through, the KSU stated in a letter to Chief Minister Conrad K Sangma on Friday.
The Union recalled that the Meghalaya State Pollution Control Board (MSPCB) had conducted the public hearing for Shree Cement on July 31, 2026, which the KSU had in its August 3 letter described as arbitrary.
It had demanded scrapping of the hearing and action against the Deputy Commissioner and Superintendent of Police of East Jaintia Hills and MSPCB officials for allegedly siding with pro-company voices and using force to prevent opponents from participating.
At a meeting on August 26, 2026, chaired by the Chief Minister, it was agreed that an FFC would examine the matter from environmental, social, legal and criminal angles to present a comprehensive picture for an informed and inclusive decision.
“It was also concluded that no activities of Shree Cement at the site would be allowed until such a decision taken,” the KSU said.
That assurance, the Union said, has not been honoured.
“But to the utter dismay, Shree Cement kept going forward with its working and activities till date even after Government decision,” the letter stated.
The KSU cited its visit to Daistong on November 7, 2026, when its members were allegedly blocked by armed men.
Despite lodging an FIR with identities and video evidence, the Union alleged no action was taken by the East Jaintia Hills police.
It demanded an immediate halt to all activities, removal of all equipment from the area, hearing of all stakeholders by the FFC, and publication of the FFC report for public scrutiny.