Addl 90 cr boosts NH-6 repair work

Shillong, Dec 31: The ongoing repair of national highway – 6 up to Malidor in East Jaintia Hills has gained momentum with the allocation of additional ₹90 crore for critical infrastructure improvements.

The work includes construction of bridges, retaining walls, and other essential works previously excluded from the project. 

A tender for these upgrades will be floated soon, ensuring the comprehensive rehabilitation of the highway.

Repair and construction activities along NH-6 extending up to Malidor are in progress as planned and are expected to be completed by March 2025, said Santa Mary Shylla, MLA of Sutnga-Saipung constituency.

The repair work has already advanced to Sonapur area and the construction is steadily moving towards Malidor. 

To expedite the process, authorities had imposed a 10-day road closure, allowing for more efficient execution of repairs.

The additional funding, secured through the upcoming tender, is set to accelerate the pace of work on critical infrastructure components, ensuring the long-term safety and usability of the highway.

Hot this week

Meghalaya man missing in Bangkok

Shillong, Jan 10: A 57-year-old Meghalaya resident, Mr. Treactchell...

Pay hike of Assam ministers, MLAs likely as 3-member panel submits report

Full report likely by Oct 30 Guwahati Sept 25: There...

ANSAM rejects Kuki’s separate administration demand, says bifurcation not acceptable

Guwahati, Sept 8: Rejecting the separate administration demand of...

Meghalaya Biological Park Inaugurated After 25 Years: A New Chapter in Conservation and Education

Shillong, Nov 28: Though it took nearly 25 years...

Meghalaya’s historic fiber paves the way for eco-friendly products and sustainable livelihoods

By Roopak Goswami Shillong, Oct 25: From making earbuds to...

Siren installed to alert water release from Ganol dam

Tura, April 17: Two sirens have been installed at...

Mizoram leaders meet Union Home Secy; discuss fencing of India-Myanmar border

Aizawl, Apr 17: The Centre urged civil society organisations...

Mamata to lay foundation stone of JSW’s 1600 MW Salboni power plant on April 21

Kolkata, Apr 17: West Bengal Chief Minister Mamata Banerjee...

Iran confirms 2nd round of nuclear talks with US will be in Rome

Dubai, Apr 17: Iran confirmed Wednesday that the next...

Markets trade lower in early trade dragged down by IT stocks

Mumbai, Apr 17: Benchmark equity indices Sensex and Nifty...

22 Naxalites arrested, explosives seized in Chhattisgarh

Bijapur, Apr 17: Twenty two Naxalites have been arrested...
spot_img

Related Articles

Popular Categories

spot_imgspot_img